Code Quiz

Q. An existing corporate data center is concerned about possible loss of power due to the fact that it is supplied by only one service. The existing feed consists of a 1600A, 208Y/120V, 3-phase, four-wire service. Data center management personnel propose to add an additional service. What are the Code-compliant options available to the data center management team?

A) An additional service cannot be added; this is a violation of 225.30.

B) An additional service can only be added if the capacity requirements exceed 2000A.

C) An additional service can only be added if it is of different characteristics. For example, it is a single-phase, 240/120V, 3-wire service.

D) An additional service identical to the existing service may be installed for “enhanced reliability.”

Answer: D

Explanation: Per a change to 230.2(A)(6) of the 2005 NEC, an additional service per 230.2(A)(6) or an additional feeder per 220.30(A)(6) may be installed for the purpose of “enhanced reliability.” The additional service or feeder may be identical to the existing service or feeder.

Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states. He can be reached at necexpert@aol.com.

Want to use this article? Click here for options!




Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What’s Wrong Here?

Jul 29, 2011 5:56 PM

What's Wrong Here?

Jul 21, 2011 3:05 PM

What's Wrong Here?

Jul 7, 2011 10:13 AM

View all What's Wrong Here?

product spotlight

Converter

Mar 6, 2012 8:26 AM

Converter

This redesigned full-power converter features fault ride-through (FRT) capability ...

View all 2012 Product Spotlights

Free Product Info

Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.

Recent Comments

More...


Social Media

More ways to stay informed...

follow us on twitter

Find us on Facebook

EC&M TV

Arlington CP9000

Arlington’s new 9” diameter ceiling cover plate is the neatest way to cover unused “high hat” cans. With no tools needed, installation couldn’t be faster!...

Arlington Gangable Boxes

Designed for new or retrofit applications, these snap-together gangable plastic boxes eliminate the need to construct a multiple-gang steel box out of several individual ones...

Listen
Sizing Gen-Sets: Facts, Hints, and Good Judgment
Listen

The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

Understanding NEC Requirements for Solar Photovoltaic Systems
During this session, Mike Holt will address possible conflicts or confusing NEC requirements, provide tips on proper electrical installation techniques, and discuss the dangers related to improper installations. View this On Demand Webinar!

Top Code Changes: 2011 NEC
EC&M has partnered with NEC expert Mike Holt to present a one hour Webinar covering the top 2011 NEC Code Changes. This event will be broadcast live on the Web with streaming audio and PowerPoint slides allowing the audience to have real-time interaction with the guest speaker, Mike Holt. View this On Demand Webinar!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

industry links

industry links

rss icon

rss

Browse Back Issues

Browse Back Issues